A project’s drawing, package list and delivery schedule can change independently. “Use the latest file” leaves each participant to decide which file is current and what changed. A short decision log links new information to its consequences, required approval and the point when the updated version becomes effective.

Identify the agreed starting version

List the documents behind the transport plan: shipment contents, package parameters, addresses, handover conditions and schedule. Record file names or version references. Nominate the customer’s coordinating contact and a backup. A single contact manages communication but does not replace engineers, receivers or documentation specialists. UNECE guidance addresses information exchange along the transport chain; allocation of decisions for your order must be agreed by its participants.

Describe each change as a decision

Record the previous agreement, proposed change and reason. Attach the new document version and identify affected packages. Changes to dimensions, contents or unloading location can require transport and related operations to be reassessed. Do not leave this information only in a technical group’s messages. The proposer must inform the transport coordinator before work proceeds under the previous arrangement.

Distinguish receipt from approval

“Received”, “under review” and “approved” mean different things. Decide who checks technical implications, confirms site readiness and approves price or schedule changes. An urgent phone call can speed communication, but its decision should then be recorded in writing. Mark unanswered requests as awaiting approval. Silence in a group chat should not automatically authorize a route change or a different set of goods.

Close the entry and communicate the outcome

After approval, record the effective date, approving participants and replaced documents. Notify the people who need the new version and identify the superseded instruction. A driver needs current applicable instructions through the agreed channel rather than the entire project history. Review open entries before the next phase. At completion, retain the final change list with handover documents so later reconciliation uses a consistent record.

  • Identify starting versions of the package list, parameters, addresses and schedule.
  • Record the reason, proposer and precise difference for each change.
  • Allocate technical, operational and commercial approvals to authorised participants.
  • Separate pending decisions from approvals and name an urgent clarification contact.
  • Distribute current instructions, mark superseded versions and retain the final record.

Leave the route and contact details to discuss your project. Email the change register to info@inlogistics.kz with your request reference. A manager will clarify the inputs and prepare a proposal.